Future of the Eel River to Russian River Trans Basin Diversion (Potter Valley Project)
Learn more about the New Eel Russian Facility from the "What is Happening to the Potter Valley Project" link in the sidebar.
Use drop down menus to explore each topic:
Articles (in order published):
- PPIC: An Opportunity to Restore Fish Abundance on the Eel Rive, 7/16/2019
- KZYX: Regulatory agency approves reduced flows through Potter Valley Project, 9/29/22
- Nor Cal Public Media: Santa Rosa looks to shore up strategy to keep Eel River water available for use, 11/7/22
- Press Democrat: Scott Dam gates to stay open, meaning Lake Pillsbury diversions to remain at drought levels, 3/16/23
- KZYX: Spillway gates on Scott Dam to remain open, curtailing flow into East Branch, 3/18/23
- Lost Coast Outpost: THE ECONEWS REPORT: Scott Dam and its Shaky Seismic Stability, 4/1/23
- The Revelator: Could California’s Next Dam Removal Take Place on This Endangered River?, 4/19/23
- Sonoma State Star: PG&E may be dammed with Eel River safety concerns, 4/25/23
- Lost Coast Outpost: Fishing and Conservation Groups Sue PG&E Alleging Harm to Salmon and Steelhead on the Eel River, 5/16/23
- Mendo Voice: Environmental, fisheries groups sue PG&E over Potter Valley Project operations, 5/17/23
- Redheaded Blackbelt: PG&E Plans to Remove Both Potter Valley Project Dams , 5/18/23
- Mendo Fever: PG&E Wants to Dial Back Water Released Into the Russian River from Lake Pillsbury, 8/6/23
- Times Standard: Multiple groups wary of new Potter Valley Project plan, 8/10/23
- PPIC: Defining Community Is Slippery on the Eel River, 8/10/23
- Mendo Fever Op Ed by Adam Gaska: If the Russian River goes dry, affluent Marin County Has as much at stake as Mendocino, 2/18/24
- Press Democrat: PG&E releases final plan for removal of Scott and Cape Horn dams and elimination of Lake Pillsbury, 2/6/25
- Lost Coast Outpost: Are the Eel River Dams Coming Down? PG&E Releases Final Decommissioning Plan and Will Give a Public Presentation About it, 2/5/25
- Ukiah Daily Journal: PG&E to give update on Potter Valley Project Thursday, 2/4/25
- Ukiah Daily Journal: Update on Potter Valley Project removal, new water-diversion designs, 2/7/25
- Eureka Times Standard: SUBSCRIBER ONLY, 2/8/25
- Mendo Fever: PG&E moves to dismantle Potter Valley Project predicting ‘adverse impacts’ to the Russian River, 2/3/25
- RedHeaded Blackbelt: Final Draft Surrender Application and Decommissioning Plan for the Potter Valley Project Available for Viewing, 2/2/25
- MendoFever: End of an Era: PG&E plans to decommission Potter Valley Hydroelectric Facility, 2/15/25
- ABC 7 KRCR: PG&E evaluating plans for Eel River Dam removal project, 2/18/25
- Unwon BREAKING: California to Spend $500 Million to DESTROY Century-Old Dam, End Water Supply for 600,000 Citizens in Fire-Prone Region, 1/27/25
- Earth Hope: Two dams slated for demolition on California’s Eel River, 2/21/25
- Eureka Times Standard: Dam removal and its discontents: Stakeholders weigh in on PG&E decommission and license surrender plan, 2/22/25
- Cal Trout: The Eel River’s Return: California’s Third Largest Watershed Is on its Way to Flowing Free and CalTrout Has a Plan for its Restoration, 2/23/25
- Lake County News: Supervisors to discuss concerns over plan to remove Scott Dam, consider letters to governor and Trump Administration, 2/24/35
- Lost Coast Outpost: Lake County May Try to Derail Eel River Dam Deal With Direct Appeal to President Trump, 2/24/25
- Lake County News:Supervisors to discuss concerns over plan to remove Scott Dam, consider letters to governor and Trump Administration, 2/24/25
- Lake County News: Supervisors approval letters to state, federal officials over concerns about proposed Scott Dam removal, 2/26/25
- SF Gate: A California reservoir could disappear if PG&E gets their way, 2/28/25
- Unwon: Rural California County Appeals to President Trump: Save Our Water!, 2/2725
- Press Democrat: ‘Remarkable’ or devastating? Concerns about Russian-Eel River water supply focus of Cloverdale town hall, 3/19/25
- Mendo Fever: Lake County calls for accountability in PG&E Dam Removal, 3/19/25
- Press Democrat: Battle lines drawn months before PG&E submits final application to decommission Potter Valley hydropower plant 3/22/25
- Mendo Fever: Lake Pillsbury’s fate sparks heated debate at Cloverdale town hall 3/24/25
- Lake County Record Bee: Dam decommission could seriously impact local economy says county-based organization 3/31/25
- Mendo Voice Opinion: Scott Dam, situated on a fault, could fail during a seismic event 4/1/25
- SF Gate: Northern California town hall erupts over PG&E's 'dangerous' reservoir plan 4/2/25
- Bohemian: Locals Up in Arms About Potter Valley Water Project 4/6/25
- The Observer (via Ukiah Daily Journal):Divisive water politics (Potter Valley Project) 4/6/25
- Mendocino Voice Opinion: Major earthquake could instantly destroy Scott Dam, scientists warn in op-ed 4/7/25
- Lost Coast Outpost: Farm Bureaus in Russian River Counties Issue Plea to President Trump to Keep the Potter Valley Dams in Place 4/9/25
- Mendocino Beacon: Huffman fields questions about water supply, democracy at Ukiah Town Hall 4/10/25
- KZYX: Local Farm Bureaus Appeal to Trump to Intervene in Potter Valley Project Decommissioning 4/14/25
- SF Gate: Northern California farmers urge Trump to prevent PG&E's dam removal 4/15/25
- Mendocino Voice Letter to the Editor: Huffman claims ‘disinformation,’ Lake Pillsbury Alliance calls foul 4/17/25
- SF Gate: Trump administration mulls intervention in California dam removal 4/18/25
- Redwood News: First Eel River Expo Arrives With A Packed House and a Stark Warning From Congressman Jared Huffman 4/21/25
- KZYX: Federal Agency is Reviewing Funding for Potter Valley Project Decommissioning 4/21/25
- San Diego Post: 600,000 Californians face water crisis as Trump plans to dismantle 100-Year-Old dam 4/21/25
- Daily Mail: Terrifying ticking timebomb crisis that could hit 600,000 California residents 4/23/25
- Ukiah Daily Journal: Federal officials reviewing the Potter Valley Project, letter states 4/23/25 and same article in Eureka's Times Standard
- Press Democrat: Amid pleas to ‘Santa Trump,’ dam removals remain on track as feds rule out takeover of PG&E’s Potter Valley plant 4/29/25
- MendoFever: Setting the record straight: Inviting Trump to interfere with the Potter Valley Project—An Op-Ed 4/29/25
- CA Sportfishing Protection Alliance: PG&E proposes “rapid removal” plan for Cape Horn and Scott dams on the Eel River 4/28/25
- Mendocino Voice Opinion from PG&E: Potter Valley Project decommissioning was economic; seismic concerns came afterward 5/3/25
- Lake County News: Canny: Potter Valley Project’s surrender and decommissioning 5/26/25
- Maven's Notebook: Friends of the Eel River - How many ways can the Potter Valley Project fail? 5/29/25
- You Tube recording Lake Pillsbury Town Hall 05/28/25
- SF Gate: PG&E customers face $532M bill for dam removal some don't want 5/29/25
- CalTrout: Six Things to Know about the Potter Valley Project and Eel River Restoration 5/29/25
- Lake County Record-Bee: Scotts Dam removal debated at Chamber sponsored forum 5/30/25
- UDJ (gift article): Life after the Potter Valley Project: ‘The water will not be cheap’ 5/31/25
- Times Standard: Opposition to Potter Valley decommission, dam removal voiced 5/31/25
- Mendo Fever: Water worries rise as leaders plan for life after the Potter Valley Project 6/3/25
- Mendocino Voice: Mendocino County Supervisor Haschak: Dams are coming down — and a new facility is going up. 6/5/25
- Mendo Fever: Town hall in Lakeport unites voices to save Lake Pillsbury 6/7/25
- Lake County News: Town hall presents opposing views on controversial plan to decommission Potter Valley Project 6/8/25
- Bohemian: Water Woes, Planned Dam Removal Threatens North Bay Water Security June 17, 2025
- Press Democrat: Close to Home: A two-basin deal is the only solution by President of Round Valley Indian Tribes 6/22/25
- Mendo Fever: In Redwood Valley, PG&E lays out bold plans — few show up to listen 7/16/25
- SF Chronicle: Two dams in Northern California could be razed under PG&E plan, 7/25/25
- SF Chronicle via MSN news Two dams in Northern California could be razed under PG&E plan, 7/25/25
- Eureka Times-Standard: Humboldt Supervisors to see full Eel River water diversion agreement 7/21/25
- Press Democrat: PG&E files long-awaited application to decommission Potter Valley Project, opening public comment window 7/25/25
- Press Democrat Editorial: Two-basin solution offers water security 7/27/25
- Ukiah Daily Journal: PG&E files Surrender Application for Potter Valley Project 7/25/25
- Mendo Fever: PG&E submits plan to tear down Potter Valley Project 7/25/25
- Eureka Times-Standard, 'This is the best we can get’: Humboldt County supes OK Potter Valley water diversion deal 7/23/25
- Lost Coast Outpost: Humboldt Supervisors OK Potter Valley Water Diversion Plan, Paving the Way for Eel River Dam Removal 7/23/25
- Trout Unlimited: The path forward for the Eel River’s fish and communities 7/24/25
- Lake County News: PG&E files final surrender application and decommissioning plan for Potter Valley Project 7/27/25
- SF Gate: Letting a Northern California river run free comes at a cost 7/29/25
- PRESS RELEASE: Major Steps Taken to Secure Water Future for the Russian River Region 7/24/25
- Marin Independent Journal: PG&E advances water project exit plan 7/28/25
- Mendo Fever: Mendocino County’s water future takes shape with $18M state investment 7/31/25
- Mendo Fever: PG&E submits plan that will erase Lake Pillsbury and change the Russian River forever 8/9/25
- San Francisco Chronicle: New California dam removal could restore a river — and destroy a community 8/9/25
- Lost Coast Outpost, THE ECONEWS REPORT: When Will the Eel River Dams Fall? 8/9/25
- Sonoma County Gazette: A watery tale of two cities 8/10/25
- Sonoma County Gazette: Potter Valley project ending: How will this impact winegrowers? It’s not all doom and gloom. Here’s a plan for growers... 8/11/25
- Mendocino Voice: Friday 8/15/25 workshop in Willits seeks to encourage fast removal of Potter Valley Project dams 8/11/25
- Lost Coast Outpost: What’s Next for Eel River Dam Removal? Find Out at Today’s Virtual Town Hall Meeting! 8/11/25
- Lost Coast Outpost: At Virtual Public Meeting Last Night, PG&E Officials Outline Next Steps for Eel River Dam Removal 8/12/25
- Active Nor Cal: PG&E Outlines Timeline to Tear Down Two Eel River Dams After 100 Years 8/13/25
- Sonoma County Gazette: Cloverdale warns: Save water now or face the squeeze later 8/14/25
- ABC 7 KRCR: PG&E to begin Eel River Dam removal amid environmental concerns 8/14/25
- Local News Matters: Letter writing workshop will urge regulators to swiftly remove Potter Valley Project dams 8/14/25
- SF Gate: 'Can’t even believe we’re talking about this’: PG&E plan shocks NorCal firemen 9/3/25
- Press Democrat: Potter Valley dam removal to aid salmon but imperil Lake Pillsbury wildlife 9/6/25
- SF Chronicle (GIFT ARTICLE): California dam removal plan blasted by Trump administration 9/8/25
- Mendo Fever: PG&E lays out plan to pull Potter Valley dams, 9/10/25
- Lost Coast Outpost: Trump Administration Slams Eel River Dam Removal Plan, But Huffman is Confident the Project Can’t Be Stopped 9/9/25
- SF Gate: Trump seizes on California dams as Newsom faces growing pressure 9/10/25
- Mendo Fever Op Ed by Adam Gaska: A tale of two rivers in Mendocino County: Where the Eel and Russian Rivers meet, 9/15/24
- Lake County News: Lake County officials challenge PG&E’s claims about Potter Valley Project’s seismic safety 9/23/25
- Lake County News: State Water Board to hold scoping meetings on Potter Valley Project decommissioning plan 10/10/25
- Ukiah Daily Journal: Proponent of dams removal argues: “You can’t own water” 10/21/25
- Ukiah Daily Journal: Supervisors delay vote on Potter Valley Project resolution 10/23/25
- Mendocino Voice: Mendocino County Board of Supervisors advances resolution on Potter Valley Project decommissioning 10/22/25
- Eureka Times Standard: Potter Valley | Mendocino County rejects resolution opposing dam removal 10/25/25
- Ukiah Daily Journal: Board of Supervisors pass revised resolution on Potter Valley Project 11/6/25
- Mendo Voice: Mendocino County supervisors narrowly back PG&E’s Potter Valley dam decommissioning plan 11/7/25
- Ukiah Daily Journal: Workshop planned in Ukiah to update community on Potter Valley Project 11/16/25
- Mendocino Voice: Ukiah workshop to address Mendocino County’s water future post–Potter Valley dams 11/19/25
- Nor Cal Public Media: Decommissioning process moves forward for Potter Valley Project dams 11/19/25
- Eureka Times Standard: Environmental groups host Potter Valley Project meetings 9/11/25
- Mendocino County: Northern California tribes join forces to restore Eel River in response to anticipated PG&E dam removal 11/13/25
- Mendocino Beacon: Board of Supervisors pass revised resolution on Potter Valley Project 11/13/25
- US News & World Report: Northern California Tribes Sign Treaty to Restore Eel River, Fish Populations, After Dams Removed 11/14/25
- Ukiah Daily Journal: Workshop planned in Ukiah to update community on Potter Valley Project 11/16/25
- Mendocino Voice: Ukiah workshop to address Mendocino County’s water future post–Potter Valley dams 11/19/25
- Nor Cal Public Media: Decommissioning process moves forward for Potter Valley Project dams 11/19/25
- Press Democrat: Water storage options floated for Mendocino County’s Potter Valley as Pacific Gas and Electric advances dam removal 11/28/25
- Ukiah Daily Journal: Water storage options discussed at forum in Ukiah 11/26/25
- SF Gate: Ukiah: Community Learns Future Of Water After Potter Valley Project Dams Are Decommissioned 11/25/25
- Maven's Notebook: POTTER VALLEY PROJECT: Department of Agriculture Asks FERC to Halt Decommissioning Process (Updated with USDA Press Release) 12/19/25
- Press Democrat: Federal administration intervenes in dispute over fate of PG&E’s Potter Valley Project 12/20/25
- Lost Coast Outpost: Federal Administration Intervenes in Potter Valley Dam Removal, as Department of Agriculture Asks FERC to Halt Decommissioning Process 12/19/25
- Eureka Times-Standard: Potter Valley Project | Feds intervene in Eel River dam removal 12/19/25
- Action News Now: USDA and Congressman Doug LaMalfa defend Potter Valley from water cuts 12/23/25
- Marin Independent Journal: US intervenes in North Coast dam controversy 12/22/25
- Mendo Local: PG&E Statement on USDA Intervention 12/22/25
- Mendocino Voice: Federal administration steps into review of proposed Potter Valley Dam removal 12/24/25
- International Water Power and Dam Construction: USDA intervenes in California hydropower decommissioning as FERC reviews Potter Valley Project 12/24/25
- Acres USA: Fish Versus Farmers? 1/20/26
- Ag Net West: Potter Valley Dam Removal Threatens California Water Supply 1/24/26
- Ag Net West: Potter Valley Water Fight Intensifies: Todd Lands Warns “This Could Happen Anywhere in California” 1/23/26
- Press Democrat: How a California tribe is confronting the Trump administration to claim their historic rights to a river 1/31/26
- Enterprise-Record: How a California tribe [Round Valley Indian Tribes] is confronting the Federal administration to claim their historic rights to a river 2/3/26
- SF Gate: Mendocino Co.: Water Commission To Discuss Storage Options Thursday Ahead Of Potter Valley Project Shuttering 2/6/26
- Local News Matters Ahead of Potter Valley Project shutdown, water commission weighs storage options [at February 12th Commission Meeting] 2/11/26
- Ukiah Daily Journal: Water storage options to be discussed at IWPC meeting Thursday[at February 12th Commission Meeting] 2/12/26
- Ukiah Daily Journal: Life after the dams: New water storage options mulled for Mendocino County 2/21/26
- Mendocino Voice: Your guide to the Potter Valley Project and what comes next 2/25/26
- Lost Coast Outpost: POTTER VALLEY DAM UPDATE: The U.S. Secretary of Agriculture Says That a Municipal Water District in Riverside County is Interested in Taking Over the Project 4/21/26
- Lost Coast Outpost: Statements From PG&E and Friends of the Eel on SoCal Agency’s Potter Valley Dam Bid 4/21/26
- GIFT ARTICLE: San Fran Chronicle: Trump administration offers plan to stop dam removal on California river 4/21/26
- Active Nor Cal: The Eel River Dam Removal Was Almost a Done Deal. Now Southern California Wants to Buy Them. 4/22/26
- Ukiah Daily Journal: PG&E reports receiving no new proposal to buy the Potter Valley Project 4/22/26
- Lost Coast Outpost: That SoCal Water Agency Says It’s Just in the Very Initial, Exploratory Phase of its Potential Bid to Take Over the Eel River Dams 4/22/26
- Eureka Times Standard: Huffman: Federal Potter Valley intervention could be catastrophic for Northern California water 4/22/26
- GIFT ARTICLE- Press Democrat: Federal Agriculture secretary touts Southern California water district as potential buyer for Potter Valley Project 4/23/26
- Redheaded Blackbelt: Feds Float Late-Stage Idea to Keep Eel River Dams as Removal Plan Moves Forward 4/23/26
- Congressmember Jared Huffman on breaking news regarding Potter Valley Project, 4/23/26
- Lost Coast Outpost: ‘This is Not OK’: Huffman Says He’ll Launch an Investigation Into the Trump Administration’s Eel River ‘Water Grab’ Scheme 4/23/26
- SF Gate: New twist emerges in battle over century-old Northern California dams 4/24/26
- Press Democrat: Huffman demands ‘clear and complete account’ of Trump officials’ role in Southern California water district’s plans for Potter Valley Project 4/28/26
- San Fran Chronicle: Congressman opens investigation into Trump administration’s involvement in California dam removal 4/28/26
- Natural Resources Committee: Huffman Demands Answers on Trump Scheme to Ship North Coast Water to SoCal District 4/28/26
- Eureka Times-Standard: Huffman demands ‘clear and complete account’ of Southern California water district’s plans for Potter Valley Project 4/28/26
- Active Nor Cal: A Congressman Just Opened an Investigation Into a Plan to Send Eel River Water to Southern California 4/29/26
- Mendocino Voice: The Potter Valley dams are coming down 5/1/26
- Ag Alert (via Maven's Notebook): New CDFW director addresses priorities, predators 5/2/26
- EcoNews Report PODCAST: new Threat to Eel River Dam Removal? 5/2/26
- Lost Coast Outpost: New Threat to Eel River Dam Removal? 5/2/26
- Eureka Times-Standard: Potential Potter Valley Project buyer suggests PG&E failed to tell ‘actual truth’ 5/2/26
- Local News Matter: Potter Valley dams to come down as SoCal interests challenge local water agreement 5/3/26
- Eureka Times-Standard OPINION: Plan to send Eel River water to SoCal is either a pipe dream or massive water grab 5/3/26
- AgNet West: Potter Valley Fight Intensifies as Community Pushes Back Against Dam Removal and Water Loss 5/5/26
- Press Democrat: ‘This is exploratory’: Southern California water agencies ramp up interest in Northern California’s Eel River dams 5/16/26
- Redheaded Blackbelt: Southern California Water Agencies Eye Potter Valley Dams as New Political Battle Emerges Over Eel River Future 5/18/26
- Mendocino Voice: The downstate bid for Mendocino’s Potter Valley Project 5/15/26
- Press Democrat Letters to the Editor, Friday May 15: Local water users deserve answers from Southern California district by Russian Riverkeeper
- KRCR ABC 7: Environmental, tribal groups urge Californians to oppose Eel River dams plan at meeting 5/14/26
- Press Democrat: 45 Potter Valley posts later, Todd Lands is distancing himself from Southern California agencies eyeing Eel River dams 5/22/26
- Mendocino Voice: The Potter Valley bid that makes no sense 5/25/26
- Press Democrat: Federal regulators signal support for Pacific Gas and Electric’s bid to decommission Eel River dams 5/26/26
- Ukiah Daily Journal: FERC to hold meetings in Ukiah on Potter Valley Project 5/28/26
- Mendocino Voice: Some animals win, some lose when the Potter Valley Project dams come down 5/27/26
- Maven's Notebook: Edward Ring EDITORIAL - An alternative vision for the Potter Valley Project 6/11/26
- Press Democrat: Cloverdale City Council’s fractious hearing on Potter Valley Project shows rifts among members 6/15/26
- PRESS RELEASE: Two-Basin Solution partners respond to meeting between USDA, Interior, PG&E, and Elsinore Valley Municipal Water District regarding Eel River Dams 6/16/26
- Native News Online: Water Agencies, Tribes and Conservation Groups Defend “Two-Basin Solution” Amid Federal Meetings on Potter Valley Project 6/16/26
- Press Democrat: [Ag Secretary Brooke Rollins] ups ante in quest to thwart removal of PG&E’s Eel River dams 6/16/26
- Cal Trout: Two-Basin Solution partners respond to meeting between USDA, Interior, PG&E, and Elsinore Valley Municipal Water District regarding Eel River Dam 6/16/26
- RFD TV: Federal Administration Evaluating California’s Potter Valley Project, Signals Support for Existing Dams 6/16/26
- Redheaded Blackbelt: Support Eel River Dam Removal at Upcoming Public Hearings, Urges Friends of the Eel River 6/17/26
- Lost Coast Outpost: Internal Documents From a Southern California Water Agency Outline a Vision to Turn Eel River Water Rights Into a Cash Bonanza — at the Expense of Local Users 6/16/26
- Ukiah Daily Journal: PG&E meets with federal officials regarding Potter Valley Project 6/18/26
- Lost Coast Outpost: Interested in Eel River Dam Removal? Friends of the Eel and the Sierra Club Redwood Chapter Urge People to Attend FERC Meetings in Ukiah Next Week 6/16/26
- Mendocino Voice: Tribe with senior Eel River water rights shut out of White House meeting 6/18/26
- Lake County Record-Bee: D.C. plan to save Scott Dam but fate remains uncertain 6/18/26
- Eureka Times Standard: Coalition expresses support for dam removal ahead of federal Potter Valley meetings 6/19/26
- Riverside Press Enterprise: Is Lake Elsinore water district ‘a legitimate buyer’ for 2 Northern California dams? 6/22/26
- Patch: Elsinore Valley Municipal Water District And Trump Appointee Spark Controversy Over Possible Acquisition 6/22/26
- Jefferson Public Radio: Eel River dam removal hearings begin in Ukiah 6/23/26
- Eureka Times Standard: U.S. Rep. Huffman discusses Potter Valley, Last Chance Grade projects 6/29/26
- Mendocino Voice: Feds take Potter Valley dam “public” comments privately Tuesday evening 6/25/26
- Lake County News: Comment period on Potter Valley Hydroelectric Project open through July 24, 7/8/26
- Ukiah Daily Journal: Ukiah has plenty of water — the Ukiah Valley doesn’t 7/11/26
- Mendocino Voice: Potter Valley update: North Coast residents split on dams, united against Southern California 7/14/26
- Ag Net: Potter Valley Water Fight Gains Federal Attention as Community Seeks to Preserve Key Infrastructure 7/23/26
- Ag Net: Keely Covello Talks Potter Valley, Water, and California’s Future with The Ag Meter 7/23/26
- Mendocino Voice: Federal regulators extend Potter Valley comment deadline to September, 7/24/26
- Mendocino Voice, Opinion: A seismic threat to the Potter Valley Project’s Scott Dam 8/18/26
- Spotify podcast: Plans to Disrupt Dam Removal Get FERC'd 8/2/26
- Mendocino Voice: New models say a rebuilt Eel River water link could keep Russian River supplied 8/19/26
- Redwood News: FERC Moves Forward With Eel River Dam Removal, Upcoming Meetings Will Allow Humboldt Residents to Weigh In 8/20/26
- Eureka Times Standard Opinion: A glimmer of hope: Eel River Dam removal hearing a chance to be part of history 8/21/26
- Eureka Times Standard: Potter Valley Project scoping meetings in Eureka give Humboldt County voice in post-dam future 8/22/26
- Redheaded Blackbelt: New Opportunity to Support Eel River Dam Removal at Eureka Meetings 8/24/26
- Press Democrat: Still time to weigh in with feds over fate of Eel River dams 8/26/26
Other:
- November 2025: Janet Pauli and Sean White were on the “Like it or Not Podcast” linked HERE, speaking about PVP decommissioning.
- November 24, 2025: Potter Valley Project Decommissioning Workshop YouTube Meeting Recording
- The Round Valley Indian Tribes issued a public letter to Secretary Rollins and Secretary Burgum regarding the decommissioning of the Potter Valley Project.
The Federal Energy Regulatory Commission published a Notice of Scoping Meeting and Request for Comments on the Proposed Surrender, Decommissioning, and Non-Project use of Project Lands (NERF) dated May 22, 2026.
FERC will prepare a document discussing the environmental impacts of both the decommissioning and the building of the New Eel Russian Facility (NERF.) FERC will use this document in its decision-making process to identify potential adverse and beneficial impacts of the proposed project surrender and reasonable alternatives. The scoping process gathers input regarding the environmental impacts of the proposal. Specifically, FERC staff request comments on potential alternatives and impacts, as well as identification of any relevant information, studies, or analyses concerning effects on the quality of the human environment.
The Comment period has been extended.
Comments are NO LONGER due Friday, July 24, 2026 but can be submitted to FERC until September 18, 2026 5:00 PM Eastern time (2 PM Pacific time.) Refer to the documents below for more information.
2026, 5-22 FERC PVP NEPA Scoping Notice.pdf2026, 5-22 FERC PVP NEPA Scoping Document.pdf2026, 7-24 FERC, time extension on comments P-77-332.pdf
Two Additional Scoping Sessions Announced
FERC has noticed two additional public scoping sessions to collect comments on the scope of the environmental issues that should be analyzed in the NEPA document. All interested individuals, resource agencies, Native American Tribes, and non-governmental organizations (NGOs) are invited to attend one or both of the sessions.
These additional sessions will follow the format of the June 23 and 24, 2026 sessions. There will be no formal presentations at either session. Numbered tickets will be handed out on a first-come, first-serve basis; individuals will be called in order by ticket number to provide oral comments to be transcribed by a stenographer for the formal record. Time limits on oral comments may be enforced to ensure those wishing to comment have the opportunity to do so. The times and locations of the additional scoping sessions are as follows:
Evening Scoping Session
DATE: Tuesday, September 15, 2026
TIME: 6:00 p.m.- 8:00 p.m. Pacific Time (PT)
PLACE: Wharfinger Building
ADDRESS: 1 Marina Way, Eureka, CA 95501
Daytime Scoping Session
DATE: Wednesday, September 16, 2026
TIME: 9:00 a.m.- 11:00 a.m. (PT)
PLACE: Wharfinger Building
ADDRESS: 1 Marina Way, Eureka, CA 95501
Related Press
2026, 5-25 IWPC Press Release on FERC scoping doc.pdfIWPC Legal Counsel Staff Report on FERC Scoping Document, June 2026.pdf- Press Democrat: Federal regulators signal support for Pacific Gas and Electric’s bid to decommission Eel River dams 5/26/26
- Ukiah Daily Journal: FERC to hold meetings in Ukiah on Potter Valley Project 5/28/26
- Redwood News: FERC Moves Forward With Eel River Dam Removal, Upcoming Meetings Will Allow Humboldt Residents to Weigh In 8/20/26
- Eureka Times Standard: Potter Valley Project scoping meetings in Eureka give Humboldt County voice in post-dam future 8/22/26
- Redheaded Blackbelt: New Opportunity to Support Eel River Dam Removal at Eureka Meetings 8/24/26
Comments to FERC:
Note: individual comments will not be posted due to quantity. See FERC eLibrary website and PG&E PVP Surrender & Decommissioning webpage for more information.
2026, 6-9 Request for Humboldt Scoping Meetings.pdf2026, 7-13 Inland Water & Power Commission comments P-77-332.pdf2026, 7-13 Potter Valley Irrigation District comments P-77-332.pdf2026, 7-15 Sonoma Co Farm Bureau comments P-77-332.pdf2026, 7-21 City of Cloverdale comments P-77-332.pdf2026, 7-21 American Whitewater comments P-77-332.pdf2026, 7-21 Humboldt County comments P-77-332.pdf2026, 7-21 Marin Conserv. Leg. comments P-77-332.pdf2026, 7-21 Elsinore Valley comments P-77-332.pdf2026, 7-22 MCRRFC&WCID comments P-77-332.docx2026, 7-22 Infrastruct comments P-77-332.pdf2026, 7-23 Two Basin Solution group comments P-77-332.pdf2026, 7-22 SCWA Water Advisory Comm comments P-77-332.pdf2026, 7-23 Lake Pillsbury Alliance comments P-77-332.pdf2026, 7-23 Crab Boat Owners Assoc. comments P-77-332.pdf2026, 7-23 Cal Trout & Trout Unlimited comments P-77-332.pdf2026, 7-23 State Water Board comments P-77-332.pdf2026, 7-23 Friends of the Eel comments P-77-332.pdf2026, 7-23 Potter Valley Tribe comments P-77-332.pdf2026, 7-23 City of Santa Rosa comments P-77-332.pdf2026, 7-23 ERPA comments P-77-332.pdf2026, 7-23 North Marin Dist comments P-77-332.pdf2026, 7-23 Sonoma County & Sonoma Water comments P-77-332.pdf2026, 7-23 CalWild comments P-77-332.pdf2026, 7-23 PCFFA & IFR (fisheries) comments P-77-332.pdf2026, 7-23 FOER, FV Corregidor comments P-77-332.pdf2026, 7-24 Save CA Salmon comments P-77-332.pdf2026, 7-24 Nor Cal Fly Fishes comments P-77-332.pdf2026, 7-24 Wyiot Tribe comments P-77-332.pdf2026, 7-24 Russian RiverKeeper comments P-77-332.pdf2026, 7-24 County of Lake comments P-77-332.pdf2026, 7-24 America First Policy Inst. comments P-77-332.pdf2026, 7-24 Mendo Farm Bureau comments P-77-332.pdf2026, 7-24 Study-Tribal Beneif. Uses of Eel Rvr comments P-77-332.pdf2026, 7-27 Sonoma Farm Bureau comments P-77-332.pdfOn April 21, 2026, US Agriculture Secretary Brooke Rollins announced on social media that she had heard from a potential buyer for the Potter Valley Project. The Elsinore Valley Municipal Water District, which serves around 160,000 residential and commercial users in western Riverside County, stated in an interview with the Eureka Times-Standard (linked below) that it “wished to emphasize that the district had absolutely no concrete plans at this stage of the game, that it hadn’t yet looked at the opportunities or constraints of taking ownership of the project, or even if doing so was legally feasible at this point in the proceedings.” It is noted in the same article that though PG&E said it cannot transfer the license to the dams, the agency said that it can still transfer the dams themselves.
Since the announcement by Secretary Rollins, responses have been covered in the press from Congressmember Huffman, and representatives from PG&E, the Eel Russian Project Authority, Inland Water & Power Commission, Friends of the Eel River, and others. Articles are linked below.
The Two Basin Solution partners continue to move forward toward a continued diversion and a transfer of the water right in cooperation with PG&E.
In July 2026, Elsinore Valley Municipal Water District filed a Motion to Intervene Late:
2026, 7-13 Lake Elsinore Motion to Intervene late P-77-332.pdf2026, 7-17 RVIT Opposition to Intervene Late EVMWD.pdf2026, 7-23 Friends of River Opposition to Intervene Late EVMWD.pdf2026, 7-23 FOER CalTrout TU Opposition to Intervene Late EVMWD.pdfFERC denied the request in the response to Elsinore Valley's late filed Motion to Intervene:
2026, 7-27 FERC denial of Lake Elsinor late MoI P-77-332.pdf
In July, Infrastruck Group filed a Motion to Intervene Late:
2026, 7-23 Infrastruck Grp to Intervene late P-77-332.pdf2026, 7-30 FOER Opposition to Intervene Late Infrastruk.pdf2026, 8-4 RVIT Opposition to Intervene Late Infrastruk.pdf2026, 8-1 Oppostion Response from Infrastruck2026, 8-5 CoUkiah Opposition to Intervene Late Infrastruk P-77-332.pdf2026, 8-10 Infrastruk Reply to CoU Opp to Intervene late P-77-332.pdfFERC denied the request in the response to Infrastruck's late filed Motion to Intervene:
2026, 8-12 FERC Denial of Infrastruk late MoI - P-77-332.pdfInfrastruck filed a Request for Reconsideration:
2026, 8-17 Infrastruk Request for Rehearing for MoI P-77-332.pdfMendocino County Inland Water & Power Commission Press Release:
IWPC Press Release-FERC denial of Infrastruk late MoI, 8.13.26.pdf
Related Articles:
(Note: gift articles often expire after 30 days of issue.)
- Lost Coast Outpost: POTTER VALLEY DAM UPDATE: The U.S. Secretary of Agriculture Says That a Municipal Water District in Riverside County is Interested in Taking Over the Project 4/21/26
- Lost Coast Outpost: Statements From PG&E and Friends of the Eel on SoCal Agency’s Potter Valley Dam Bid 4/21/26
- GIFT ARTICLE: San Fran Chronicle: Trump administration offers plan to stop dam removal on California river 4/21/26
- Active Nor Cal: The Eel River Dam Removal Was Almost a Done Deal. Now Southern California Wants to Buy Them. 4/22/26
- Ukiah Daily Journal: PG&E reports receiving no new proposal to buy the Potter Valley Project 4/22/26
- Lost Coast Outpost: That SoCal Water Agency Says It’s Just in the Very Initial, Exploratory Phase of its Potential Bid to Take Over the Eel River Dams 4/22/26
- Eureka Times Standard: Huffman: Federal Potter Valley intervention could be catastrophic for Northern California water 4/22/26
- GIFT ARTICLE- Press Democrat: Federal Agriculture secretary touts Southern California water district as potential buyer for Potter Valley Project 4/23/26
- Redheaded Blackbelt: Feds Float Late-Stage Idea to Keep Eel River Dams as Removal Plan Moves Forward 4/23/26
- Congressmember Jared Huffman on breaking news regarding Potter Valley Project, 4/23/26
- Lost Coast Outpost: ‘This is Not OK’: Huffman Says He’ll Launch an Investigation Into the Trump Administration’s Eel River ‘Water Grab’ Scheme 4/23/26
- SF Gate: New twist emerges in battle over century-old Northern California dams 4/24/26
- Press Democrat: Huffman demands ‘clear and complete account’ of Trump officials’ role in Southern California water district’s plans for Potter Valley Project 4/28/26
- San Fran Chronicle: Congressman opens investigation into Trump administration’s involvement in California dam removal 4/28/26
- Natural Resources Committee: Huffman Demands Answers on Trump Scheme to Ship North Coast Water to SoCal District 4/28/26
- Eureka Times-Standard: Huffman demands ‘clear and complete account’ of Southern California water district’s plans for Potter Valley Project 4/28/26
- Active Nor Cal: A Congressman Just Opened an Investigation Into a Plan to Send Eel River Water to Southern California 4/29/26
- Mendocino Voice: The Potter Valley dams are coming down 5/1/26
- Ag Alert (via Maven's Notebook): New CDFW director addresses priorities, predators 5/2/26
- EcoNews Report PODCAST: new Threat to Eel River Dam Removal? 5/2/26
- Lost Coast Outpost: New Threat to Eel River Dam Removal? 5/2/26
- Eureka Times-Standard: Potential Potter Valley Project buyer suggests PG&E failed to tell ‘actual truth’ 5/2/26
- Local News Matter: Potter Valley dams to come down as SoCal interests challenge local water agreement 5/3/26
- Eureka Times-Standard OPINION: Plan to send Eel River water to SoCal is either a pipe dream or massive water grab 5/3/26
- AgNet West: Potter Valley Fight Intensifies as Community Pushes Back Against Dam Removal and Water Loss 5/5/26
- Press Democrat: ‘This is exploratory’: Southern California water agencies ramp up interest in Northern California’s Eel River dams 5/16/26
- Redheaded Blackbelt: Southern California Water Agencies Eye Potter Valley Dams as New Political Battle Emerges Over Eel River Future 5/18/26
- Mendocino Voice: The downstate bid for Mendocino’s Potter Valley Project 5/15/26
- Press Democrat Letters to the Editor, Friday May 15: Local water users deserve answers from Southern California district by Russian Riverkeeper
- KRCR ABC 7: Environmental, tribal groups urge Californians to oppose Eel River dams plan at meeting 5/14/26
- Press Democrat: 45 Potter Valley posts later, Todd Lands is distancing himself from Southern California agencies eyeing Eel River dams 5/22/26
- Mendocino Voice: The Potter Valley bid that makes no sense 5/25/26
- PRESS RELEASE: Two-Basin Solution partners respond to meeting between USDA, Interior, PG&E, and Elsinore Valley Municipal Water District regarding Eel River Dams 6/16/26
- Native News Online: Water Agencies, Tribes and Conservation Groups Defend “Two-Basin Solution” Amid Federal Meetings on Potter Valley Project 6/16/26
- Press Democrat: [Ag Secretary Brooke Rollins] ups ante in quest to thwart removal of PG&E’s Eel River dams 6/16/26
- Lost Coast Outpost: Internal Documents From a Southern California Water Agency Outline a Vision to Turn Eel River Water Rights Into a Cash Bonanza — at the Expense of Local Users 6/16/26
See drop down: "Updated Weekly, Decommissioning Related Articles & Press Releases" for more articles.
Notice of Availability of the Scoping Report for the Potter Valley Hydroelectric Project Surrender and Decommissioning Project
On May 12, 2026, the State Water Resources Control Board (State Water Board or SWRCB) posted the Scoping Report for the Potter Valley Hydroelectric Project Surrender and Decommissioning Project (Scoping Report). The Scoping Report summarizes comments received during the State Water Board’s Notice of Preparation of an Environmental Impact Report for the Potter Valley Hydroelectric Project Surrender and Decommissioning Project public comment period, which closed on November 3, 2025.
Link to the Scoping Report on Maven's Notebook website
Additional information related to the Potter Valley Hydroelectric Project can be found on the State Water Board’s Potter Valley Hydroelectric Project webpage: SWRCB Potter Valley Hydroelectric Project webpage
Questions regarding the Scoping Report or Potter Valley Hydroelectric Project: please contact Wilhelmina Chon, Project Manager by email at: Wilhelmina.Chon@waterboards.ca.gov.
On June 9, 2026, PG&E requested an extension of the June 30, 2026, deadline to submit evidence of its Clean Water Act (“CWA”) Section 401 water quality certification request to the California State Water Resources Control Board for PG&E’s July 25, 2025 application to surrender the license and decommission the Project. See the document linked below for more information.
2026, 6-9 PGE request time ext on wtr quality info.pdf
Special Informational Public Workshop Meeting, Monday, November 24, 2025, 1-4 PM
The Future of Our Water—the Potter Valley Project Decommissioning
Place: Ukiah Valley Conference Center/ Cabernet Rooms, 200 S. School Street, Ukiah
Time: 1 to 4 pm—Hybrid meeting Zoom Link
Join Zoom Meeting at https://us02web.zoom.us/j/82395871308 Meeting ID: 823 9587 1308
Dial in by phone: 669 900-6833
The Mendocino County Inland Water and Power Commission (IWPC) will host an informational public workshop on Monday, November 24, from 1:00–4:00 p.m. at the Ukiah Valley Conference Center to discuss the decommissioning of the Potter Valley Project , its potential impacts, and what’s being done to ensure the region’s future water supply.
The workshop will provide factual updates, answer questions, and support a collaborative, informed dialogue about this complex and evolving issue. With growing public interest, including recent discussions by the Mendocino County Board of Supervisors at multiple meetings, it is an important time to bring the community together to hear directly from agencies and experts working on long-term water solutions. There will be a Q&A session at the end of the presentations.
The Potter Valley Project, owned by PG&E, is in the process of being decommissioned, a process that carries significant implications for water supply, habitat, and infrastructure in both the Eel and Russian River watersheds. IWPC and regional partners have been working for years to plan for a post-Potter Valley Project future, secure continued water diversions, and develop new agreements that protect local water reliability while meeting state and federal requirements.
Speakers will include:
- Scott Shapiro, legal counsel for IWPC & ERPA
- Dave Manning, Executive Director of the Eel Russian Project Authority
- Tom Johnson, New Eel Russian Facility (NERF) engineering specialist
- Moderator, Janet Pauli
Attendees will receive updates on planning efforts, future infrastructure needs, existing agreements, timelines related to PG&E’s decommissioning application and ongoing storage investigations from Potter Valley and south within the Russian River watershed.
The workshop is intended to help the public better understand the facts, dispel misinformation, and engage constructively in one of the most significant water supply issues facing the region.
Hosted by: Mendocino County Inland Water and Power Commission (IWPC)
The event is open to the public, water users, local agencies, and community partners.
For more information, contact Candace Horsley at CHORSLEY@MendoIWPC.com
- 2025, 11-24 IWPC special public workshop meeting agenda.pdf2025, 11-14 Press release- IWPC workshop on PVP Nov 24, 2025.pdf
- Ukiah Daily Journal: Workshop planned in Ukiah to update community on Potter Valley Project 11/16/25
- Mendocino Voice: Ukiah workshop to address Mendocino County’s water future post–Potter Valley dams 11/19/25
- Nor Cal Public Media: Decommissioning process moves forward for Potter Valley Project dams 11/19/25
Janet Pauli and Sean White were on the “Like it or Not Podcast” linked HERE, speaking about PVP decommissioning.
October 2025:
On October 31, 2025 FERC issued the public comment period for PG&E’s application for Surrender of License and Non-Project Use of Project Lands. Deadline for filing comments, motions to intervene, and protests is December 1, 2025 5:00 PM EASTERN TIME (2:00 PM Pacific Time.)
2025, 10- 31 FERC Notice of comment period for PGE PVP Decommissioning.pdfComments submitted to FERC:
Note: The number of comments became too cumbersome to track thoroughly. All submissions can be found on the FERC eLibrary website, docket number: P-77-332
Notice of Preparation and Scoping Meetings for an Environmental Impact Report on PG&E’s PVP Decommissioning Plan
The State Water Resources Control Board staff released a Notice of Preparation (NOP) and Scoping Meetings for an Environmental Impact Report for the Potter Valley Hydroelectric Project Surrender and Decommissioning. You can find the NOP and information on the scoping meetings in the document linked below and on the State Water Board's webpage. Comments are due by 4:00 pm on Monday November 3, 2025. See the document for more information.
SWRCB Potter Valley Hydroelectric Project webpage
2025, 9-22 SWRCB PVP Notice of Preparation.pdf
On August 11, 2025 from 3 to 5 p.m., PG&E hosted an online meeting to share information on the Potter Valley Project Surrender Application and Decommissioning Plan. During the town hall PG&E discussed the overall regulatory process and noted opportunities for public participation in the regulatory process.
A recording and copy of the slide presentation will be made available by PG&E soon on the project page.
- Lost Coast Outpost: At Virtual Public Meeting Last Night, PG&E Officials Outline Next Steps for Eel River Dam Removal 8/12/25
- Active Nor Cal: PG&E Outlines Timeline to Tear Down Two Eel River Dams After 100 Years 8/13/25
Materials From Meeting:
ERPA Slide Presentation for 8-11-25 PGE Town Hall
On July 25, 2025, Pacific Gas and Electric Company filed its Final Surrender Application and Final Non-Project Use of Project Lands Application (NPUPL) for the Potter Valley Hydroelectric Project (FERC No. P-77) with the Federal Energy Regulatory Commission (FERC). This submittal package contains two applications:
- PG&E’s Final Surrender Application and decommissioning plan for its Potter Valley Hydroelectric Project that includes the removal of Project facilities and features, including, but not limited to, Scott Dam and Cape Horn Dam, and the removal of the Project from FERC jurisdiction; and
- An application for NPUPL that seeks FERC’s authorization for PG&E to allow the Eel-Russian Project Authority (ERPA) (a joint powers authority formed by a joint exercise of powers agreement between the County of Sonoma, Sonoma Water, and the Mendocino County Inland Water and Power Commission) to construct the proposed New Eel-Russian Facility (NERF) for the purpose of future water diversion from the Eel River through the Project’s existing water diversion system to the Russian River Watershed.
An electronic version of this filing is available on the FERC website at https://www.ferc.gov/docs-filing/elibrary.asp. This document can also be accessed from the following website: https://www.pottervalleysurrenderproceeding.com/ on the Documents page using the following password: PV_Surrender.
Documents are also linked below:
2025 7-25 PGE App for PVP Lic Surrender Cover Letter.pdf2025 7-25 PGE App for PVP Lic Surr Volume 1A.pdf2025 7-25 PGE App for PVP Lic Surr Volume 1B.pdf2025 7-25 PGE App for PVP Lic Surr Volume 2 Exhibit E Pt 1.pdf2025 7-25 PGE App for PVP Lic Surr Volume 2 Exhibit E Pt 2.pdf2025 7-25 PGE App for PVP Lic Surr Volume 2 Exhibit E Pt 3.pdf2026, 6-9 PGE ext request Wtr Qlty Cert 77-332.pdf2026, 7-17 FERC granting ext request Wtr Qlty Cert 77-332.pdfPG&E’s Final Draft Surrender Application and Conceptual Decommissioning Plan (Surrender Application) and Application for Non-Project Use of Project Lands for the Potter Valley Hydroelectric Project (FERC Project No. 77) is available for review at the following website: http//pottervalleysurrenderproceeding.com. This document can be accessed from the Documents page using the following password: PV_Surrender
In late 2023, PG&E received a proposal from Sonoma County Water Agency, Mendocino County Inland Water and Power Commission, Humboldt County, Round Valley Indian Tribes, California Trout, Trout Unlimited, and California Department of Fish and Wildlife, collectively referred to as the “Two-Basin Partners”, related to the decommissioning of Cape Horn Dam and associated diversion facilities. PG&E and the Two-Basin Partners have since collaborated to identify a regulatory pathway that would allow for the construction of the New Eel-Russian Facility (NERF) during decommissioning of Cape Horn Dam to minimize construction impacts to the Eel and Russian River basins, while facilitating activities related to NERF.
This file contains two applications:
- PG&E’s Draft Application for Surrender of License, and
- A draft application requesting the Federal Energy Regulatory Commission (FERC) to authorize non-Project Use of Project lands to allow the Eel-Russian Project Authority (ERPA) (a joint powers authority formed by a joint exercise of powers agreement between the County of Sonoma, Sonoma Water, and the Mendocino County Inland Water and Power Commission) to modify existing Project works and construct the NERF on lands within the FERC Project boundary.
PG&E solicited comments from Tribes, regulatory agencies, and other interested parties on the Draft Application for Surrender of License and Application for Non-Project Use of Project Lands. The public comment period closed on March 3, 2025. PG&E will address comments as appropriate before distribution of the Final Surrender Application in July 2025.
On Thursday, Feb. 6, 2025 PG&E hosted an online meeting to share information on the final draft, discussed the regulatory process, and noted opportunities to participate. Presentation linked below. See articles linked below for more information.
Slides from presentation: 2025, 2-6 PG&E DRAFT PVP License Surrender Application slides.pdf
On April 28, 2025, PG&E issued the following to those on the service list or those who responded to PG&E’s Initial or Draft Surrender Application and Decommissioning Plan for PG&E Potter Valley Hydroelectric Project, Federal Energy Regulatory Commission (FERC) Project No. 77.
PG&E distributed the Draft Surrender Application on January 31, 2025 to resource agencies, Tribes, non-governmental organization, and the interested public for public review and comment on January 31, 2025. PDF versions of the comments received are posted on PG&E’s Public SharePoint site: http//pottervalleysurrenderproceeding.com (password: PV_Surrender). These comments are being considered in the development of the Final Surrender Application.
PG&E will be filing the Final Surrender Application with FERC on or before July 29, 2025. FERC will issue a public notice upon receiving the Final Surrender Application that will include a comment period and schedule. PG&E will begin development of the proposed plans and measures in August 2025 following filing of the Final Surrender Application.
State Water Resources Control Board Comments to PG&E 2025, 03-03.pdfLake County Board of Supervisors Comments to PG&E 2025, 03-03.pdfAmerican Whitewater Comments to FERC, 2025, 03-04.pdfLake County Comments to FERC. 2025, 3-13.pdfSWRCB supplemental Comments on PG&E Draft surr. 2025, 03-24.pdf2025, 8-14 City of Rio Dell comment to FERC.pdf
Updated February 2025
Two Basin Partnership Memorandum of Agreement (MOU)
FROM THE PRESS DEMOCRAT, FEBRUARY 12, 2025:
Stakeholders on the Eel and Russian rivers have reached agreement on a framework for future water diversions from the Eel into the Russian River, once PG&E decommissions its Potter Valley power plant, through which flows have been directed for nearly 120 years.
A memorandum of understanding to be signed in a ceremony in Sacramento on Thursday [February 13, 2025] allows for limited diversions to continue, but only when the Eel River has sufficiently high flows to accommodate different life stages of federally protected salmon and steelhead trout.
The mostly wintertime diversions will reduce annual transfers into the Russian River watershed from a current level of about 40,000 acre-feet a year to about 35,000 acre-feet. (An acre-foot is equal to 325,851 gallons, or about the amount of water needed to flood most of a football field one foot deep.)
PG&E’s water rights for the diverted flows will be transferred to the Round Valley Indian Tribes, which will collect $1 million a year from Sonoma and Mendocino County users in exchange for diverted flows.
Russian River users also will pay $750,000 to $1 million annually into an Eel River restoration fund to pay for fish recovery and environmental restoration efforts on the Eel River, which has long been impacted negatively by diversions and dams in the river.
The agreement will stand for a 30-year term plus a possible 20-year renewal, but Russian River users are intended to wean themselves from the Eel River by developing new water storage and supply solutions.
Parties to the agreement also agree to endeavor to raise $50 million or more for new diversion facilities and $50 million or more for additional restoration funding.
Signatories include the Sonoma County Water Agency, known as Sonoma Water, the Mendocino County Inland Water and Power Commission, Humboldt County, the Round Valley Indian Tribes, Trout Unlimited, California Trout and the California Department of Fish and Wildlife.
Two Basin Partnership Final signed MOU, February 2025.pdfMCIWPC MOU Press Release 2-11-25.pdf
Related Articles:
- San Fran Chronicle via MSN: Dam removal deal could create longest free-flowing California river, 2/13/25
- Press Democrat: Eel River pact redresses past wrongs, provides model for compromise among diverse interests, officials say, 2/13/25
- Press Democrat: Eel, Russian River deal reached - Historic pact on future waterflows a lifeline for Sonoma, Mendocino, 2/14/25
- CA Department of Fish & Wildlife: Natural Resources Agency Thanks Tribal Leaders, Northern California Counties and Conservation Groups for Their Leadership as Historic Agreement Announced to Secure Water Reliability in the Russian River, Benefit Salmon on the Eel River, 2/13/25
- Trout Unlimited: Breakthrough for the Eel-A new agreement promises to resolve decades of conflict over water use on California’s third largest watershed––and a legendary salmon and steelhead river, 2/13/25
- California Trout Press Release: Regional Partners Sign Historic MOU on Eel River Recovery, 2/13/25
- Eureka Times Standard: ‘The dams will come out’: Humboldt County supervisors sign onto historic Potter Valley water diversion agreement, 2/11/25
- Lost Coast Outpost TODAY in SUPES: Board OKs Agreement on Potter Valley Project Decommissioning and New Eel-Russian Diversion Facility, 2/11/25
- Jefferson Public Radio: Humboldt County Supervisors sign onto historic water agreement for Eel River, 2/12/25
- Redheaded Blackbelt: Humboldt Approves Agreement as End of Potter Valley Project Nears, 2/17/25
- BC 7 KRCR: Multiple agencies sign agreement for Eel River infrastructure, 2/17/25
- Lost Coast Outpost THIS WEEK IN SUPES: Humboldt Supervisors Consider Next Steps for Decommissioning the Potter Valley Project, 2/10/25
- Eureka Times Standard: Eel River diversion agreement on Humboldt County Board of Supervisors agenda, 2-10-25
- Press Democrat: PG&E releases final plan for removal of Scott and Cape Horn dams and elimination of Lake Pillsbury, 2/6/25
- Lost Coast Outpost: Are the Eel River Dams Coming Down? PG&E Releases Final Decommissioning Plan and Will Give a Public Presentation About it, 2/5/25
- Ukiah Daily Journal: PG&E to give update on Potter Valley Project Thursday, 2/4/25
- Ukiah Daily Journal: Update on Potter Valley Project removal, new water-diversion designs, 2/7/25
- Eureka Times Standard: PG&E moves closer to surrender and decommission of Potter Valley Project, 2/ 8/25
- EcoNews Report Podcast by Friends of the Eel: A Deal for the Eel? February 2025\
- E+E Leader: California’s Watershed Agreement Ends Century-Old Water Dispute Over Eel River, 2/18/25
- Redwood News: A Conversation With Friends of the Eel River on the New Potter Valley Project Agreement, 2/19/25
- Press Democrat Editorial: Historic North Coast water deal takes shape, 2/23/25
- Healdsburg Tribune: ‘Historic Pact’ Signed Regarding Healdsburg’s Water Source, 2/23/25


PG&E submitted the letter linked below to FERC, adjusting the timeline for the Potter Valley Project surrender application and decommissioning plan.
2025, 1-24 Surrender App Schedule Update.pdf
October 2024
The Potter Valley Tribe is utilizing a California Environmental Protection Agency (CalEPA) Environmental Justice Action grant to address critical ecological concerns in the future of the trans basin diversion.
"The Potter Valley Tribe's efforts to participate in Potter Valley Project proceedings as a sovereign nation were hindered by historic inequities stemming from a more than 20-year period when the Tribe’s federal status was terminated. Only in 1993 was the tribe able to resume governance and receive federal assistance. Mike Shaver, Water Resources Manager for the Tribe, noted, "We're building our capacity to participate in regional water management decisions. This grant is helping us have a voice in issues that directly affect our people." The Potter Valley tribe has lands in both the Eel and Russian River watersheds and is seeking high level participation in future decision making in Potter Valley Project decommissioning and the prospective new trans-basin water diversion of the Eel-Russian Project Authority."
From: North Coast Regional Water Quality Control Board Executive Officer's Report, October 3-4, 2024 (Pg3)
https://pottervalleytribe.com/
Potter Valley Tribe Motion to Intervene, July 2025, Corrected December 2024
The Potter Valley Tribe filed a motion to intervene regarding the ongoing development of the Final Draft Surrender Agreement and the Final Surrender Application and Decommissioning Plan by PG&E. “Despite … extensive measures, the Tribe currently is not party to any of the major discussions or proceedings regarding the Project.” “The Tribe has now chosen to move for intervention in an exhaustive effort to be fairly included in the conversations that determine the divestment of the facilities and waters on their ancestral lands.”
2024, 7-16 Potter Valley Tribe Motion to Intervention.pdf
On July 1, 2024, FERC issued acknowledgement and acceptance of PG&E’s request to delay the submission of the Potter Valley Project decommissioning plan by six months.
2024, 7-1 FERC approval of PG&Es revised decommissing plan schedule.pdf
US Bureau of Reclamation Commissioner Camile Touton joined Congressmember Jared Huffman and David Rabbitt, Chair of the Eel-Russian Project Authority for a site visit on Friday, June 7, 2024 to Scott Dam, Cape Horn Dam, and Coyote Valley Dam at Lake Mendocino. They announced the $2 million Infrastructure Investment grant to Sonoma Water which will support the design of a new transfer pump station to meet the goals of the two-basin solution.

- MendoFever: Federal Funds Propel Eel River Water Diversion Forward, 6/9/24
- Times-Standard: Federal officials give update on Two-Basin Solution during visit to Ukiah, 6/8/24
- (same article in Ukiah Daily Journal and Willits News)
Updated December 19, 2023
The U.S. Bureau of Reclamation announced on December 19, 2023 a $2 million grant to Sonoma County Water Agency (Sonoma Water) meant to study a diversion from the Eel River to the Russian River that will have the least possible impact on salmon and steelhead.
Press Release also ran in the following:
- US Congressmember Jared Huffman website
- Redheaded Blackbelt
- Press Bee
- Ukiah Daily Journal
- Sonoma County Gazette
PG&E has made an Extension of Time request to the Federal Energy Regulatory Commission (FERC) for their final draft of the Surrender Agreement that they are curating for the Potter Valley Project dams. PG&E made this request so that they may submit for comments to be made on their draft in January 2025, instead of June 2024. Along with this, they requested that the Final Surrender Agreement be submitted in June of 2025, instead of January 2025 – which was agreed upon previously. PG&E says that by extending this time, they will have more success in consulting with various organizations and agencies to make a better Surrender Agreement and a quicker path for the decommissioning of the Potter Valley Project.
PG&E states that they are going to support the proposal of a new Eel-Russian Facility and will enter into legal agreements with the Eel-Russian Project Authority to address construction, permitting, and transferring the facility. Along with this, they would like to enter into legal agreements with agencies and parties whose interests fall outside of the FERC Surrender process.
- MendoFever: Why is PG&E Requesting an Extension on its Surrender Application of the Potter Valley Project? 6/10/24
- Lost Coast Outpost: PG&E Asks for Delay in Eel River Dam Decommissioning, 6/4/24
For more information about ERPA Meetings: https://www.eelrussianauthority.org/events/meeting
Sign-up for newsletter updates (bottom of home page) on the Eel-Russian Facility Authority at https://www.eelrussianauthority.org/
PG&E has reviewed the proposal provided by the Project Proponents determining there are aspects of the proposal which do not align with its goal of completing the decommissioning of the Potter Valley Project within the schedule approved by FERC. Therefore, the proponent’s request to construct the new Eel-Russian facility under FERC’s jurisdiction will not be included in PG&E’s Final Draft Surrender Application and Decommissioning Plan. PG&E is encouraged to see broad stakeholder support of the proposal and supports completion of the new facility in a separate but parallel path to PG&E’s decommissioning. To facilitate that path, PG&E will include those portions of the proposal that will not otherwise delay dam removal and will continue to engage with the proponents on a solution which addresses both parties’ goals. Eel Russian Project Authority (ERPA) representatives believe a path forward for continued diversions still exists and the work continues. PG&E stated it will support and facilitate that work where it can and remains committed to continue working together. North Coast U.S. Rep. Jared Huffman is not dismayed, emphasizing his committment to a Two Basin Solution and that continued diversion is not dependent on partnership with PG&E.
Read more:
- Mendocino County Inland Water & Power Commission (IWPC) 2/14/24 Update
- Mendo Fever: PG&E's Hesitation Casts Shadow on Eel-Russian River Diversion Plan, 2/14/24
- GIFT ARTICLE: Press Democrat- PG&E decision jeopardizes Eel River diversions that keep the Russian River flowing year-round, 2/11/24
- Ukiah Daily Journal: PG&E drops diversion options from its PVP proposal, Mendocino County officials report, 2/7/24 Or the same article in Willits News: 2/7/24
- Mendo Fever: Mendocino County Leaders on the Eel-Russian River Diversion, 2/15/24
Mendocino County Inland Water & Power Commission, Sonoma Water, and Sonoma County form the Eel-Russian Project Authority
Updated February 12, 2024
The Eel Russian Project Authority (ERPA) held its first meeting on Wednesday 1/31/24, appointing Sonoma County Supervisor David Rabbit as Chair and Mendocino County Inland Water & Power Commission Chair Janet Pauli as Vice Chair. Sonoma Water Agency is acting as the interim Secretary. Sonoma Water staff reviewed the Eel River diversion options and funding. A large consent calendar addressing the business of the Authority was passed unanimously. More information, including handouts, is available on the website: https://www.eelrussianauthority.org/
Updated December 8, 2023
PRESS RELEASE: The Sonoma County Board of Supervisors, who also serve as the Board of Directors for the Sonoma County Water Agency, voted today to approve a Joint Exercise of Powers Agreement with Mendocino County Inland Water and Power Commission to form the Eel-Russian Project Authority.
The new entity will have the power to negotiate with the Pacific Gas and Electric Company (PG&E) as the utility moves ahead with plans to surrender operations of the Potter Valley Hydroelectric Project and to decommission the Scott and Cape Horn dams on the Eel River. The new authority will also have the legal capacity to own, construct and operate a new water diversion facility near the Cape Horn dam.
“This is another important step in the process to find a truly regional solution to the challenges facing the Eel and Russian River watersheds,” said Sonoma County Supervisor and Sonoma Water Director David Rabbitt. “We’re grateful to all of the partners who are working diligently to achieve our co-equal goals of continued diversions into the Russian River and improving fisheries in the Eel River.”
The Potter Valley Project, currently owned and operated by PG&E, has been diverting water from the Eel River into the Russian River watershed for more than a century, playing a critical role in supplying water for agriculture, homes, and instream flows to benefit aquatic ecosystems and threatened salmonids in Mendocino and Sonoma counties.
The Potter Valley Project is licensed by the Federal Energy Regulatory Commission. In 2019, PG&E announced that it would not proceed with relicensing the project and would instead enter into a license surrender and decommissioning process. PG&E stated that its application would propose to remove Scott and Cape Horn dams and end any operations, including water diversions to the Russian River, unless it received a complete and credible proposal by July 2023.
To meet this deadline, in July, the Mendocino County Inland Water and Power Commission, the Round Valley Indian Tribes and Sonoma Water submitted a proposal to PG&E to preserve water diversions into the Russian River, while also prioritizing upstream and downstream fish migration in the Eel River. The California Department of Fish and Wildlife, County of Humboldt, California Trout and Trout Unlimited subsequently signed on to a revised proposal in November.
PG&E released an initial draft surrender application on Nov. 17, 2023 which includes several of the measures proposed by the coalition. PG&E is set to release a final draft surrender application in June 2024. The final application is expected to be submitted by Jan. 29, 2025.
The New Eel-Russian Facility proposal submitted to PG&E also called for the creation of a regional entity, which today’s board action will move forward, with the capacity to develop a yet-to-be designed facility that would allow for ongoing water diversions through the Potter Valley Project’s tunnel between the Eel River and Russian River, while providing for fish migration to support naturally reproducing and self-sustaining native fish populations.
The Eel-Russian Project Authority’s five-member board of directors will initially consist of two representatives from the Mendocino County Inland Water and Power Commission, one from Sonoma Water, one from the County of Sonoma and one from the Round Valley Indian Tribes.
For more information, visit https://sonomawater.org/pvp and https://mendoiwpc.com/iwpc-pvp-updates/
Due to the ongoing FERC Regulatory Surrender process of the Potter Valley Project and reduced water storage capacity in Lake Pillsbury due to seismic risk at Scott Dam, PG&E no longer intends to replace the inoperable Potter Valley transformer.
More information can be found in the following documents:
2024, 11-21 FERC response RE Transformer Outage.pdf2023, 3-23 PGE notice on Transformer Replacment.pdf2022, 12-15 PG&E Transformer Replacement Update.pdf2022, 2-7 PGE Cape Horn Transformer Replace.pdf
On November 17th, PG&E released the Initial Draft Surrender Application and Conceptual Decommissioning Plan (SA) for public review at the following website: pottervalleysurrenderproceeding.com
The initial draft can be accessed from the DOCUMENTS PAGE using the Password: PV_Surrender
The public comment period will be open until December 22, 2023. Formal comments must be submitted in writing via email to PVSurrender@pge.com or by mail.
PG&E will address comments as appropriate before distribution of the Final Draft Surrender Application in June 2024.
The initial draft includes PG&E’s conceptual decommissioning plan and a third-party proposal for modifications of the former Cape Horn Dam site and Van Arsdale Diversion, as necessary, to construct a New Eel-Russian Facility. PG&E has not accepted the proposal at this time but is including it as an option for Cape Horn Dam. Proponents of the proposal include California Department of Fish and Wildlife (CDFW) California Trout, Humboldt County, Mendocino County Inland Water and Power Commission, the Round Valley Indian Tribes, Sonoma County Water Agency, and Trout Unlimited. A copy of the Proponent’s Proposal is available at: https://www.sonomawater.org/pvp.
PG&E is soliciting comments from Tribes, regulatory agencies, and other interested parties on the Initial Draft Surrender Application that includes PG&E’s conceptual decommissioning plan and the Proponent’s proposal for Cape Horn Dam site and Van Arsdale Diversion.
The Initial Draft Surrender Application does not include an environmental analysis. The environmental analysis will be included in the Final Draft Surrender Application, which will be available for public review in June 2024.
- Press Democrat: PG&E formalizes plan to eliminate Lake Pillsbury in Mendocino National Forest in landmark move, 11/17/23
- North Coast Journal: PG&E Moves Forward with Eel River Dam Removal, Utility's plans have demolition starting as soon as 2028, 11/23/23
- Lake County News: Supervisors to discuss PG&E’s Potter Valley Project decommissioning plan, 12/4/23
- Mendocino Voice: Decommissioning the Potter Valley Project: a turning point for Mendocino County, 12/11/23
- Nor Cal Public Media: New regional body formed to transform Potter Valley Project, 12/6/23
- Lake County Record-Bee: PG&E draft plans for Scott Dam, pilloried as tone deaf - BOS condemns PG&E for excluding Lake Co. from plans, 12/11/23
- Marin Independent Journal: Marin water suppliers laud Mendocino water diversion plan, 12/9/23
- Sonoma County Gazette: Sonoma and Mendocino counties unite with Round Valley Indian tribes to preserve vital water resources, 12/14/23
On August 7, 2023, the Mendocino County Inland Water and Power Commission (MCIWPC), the Round Valley Indian Tribes (RVIT), and the Sonoma County Water Agency (Sonoma Water) submitted a proposal to advance a regional solution for preserving flows in the Russian River and improving Eel River fisheries.
On October 3, 2023, PG&E issued a statement on the Proposal for Potter Valley Project’s Draft Surrender Application and Decommissioning Plan :
PG&E has made a non-binding acceptance in concept of the Sonoma County Water Agency, Mendocino County Inland Water and Power Commission and the Round Valley Indian Tribes proposal and agrees to include it in our November 15th 2023 initial draft Surrender Application and Decommissioning Plan (SA). The acceptance of this proposal is non-binding and allows for continued discussion and public comment. The initial Draft SA will be available for public review in November 2023 and will also include PG&E’s proposal to remove Cape Horn Dam. This proposal states that it has co-equal objectives of fish migration and water diversions. PG&E will include both the third-party proposal as well as our decommissioning plan in our initial Draft Surrender Application and Decommissioning Plan.
- Press Democrat: Sonoma, Mendocino county water managers propose pathway for continued Eel River diversions, 8/8/23
- Ukiah Daily Journal: Potter Valley Project: New plan to conserve Eel River diversions submitted to PG&E, 8/8/23
- Times-Standard: Multiple groups wary of new Potter Valley Project plan, 8/10/23
- KZYX: Half-hour special on Potter Valley proposal, 8/16/23
- MendoFever: Mendocino & Sonoma County Water Interests Team-up with Round Valley Tribe to Take Over Potter Valley Project, 8/9/23
- Press Democrat Editorial: No one will win a North Coast water war, 8/13/23

In March 2023, PG&E notified local agencies that
"out of an abundance of caution and in the interest of community safety, PG&E has made the decision to keep the spillway gates atop Scott Dam at Lake Pillsbury in Lake County open this spring and in future years. This will result in lower summer lake levels and less water being released from Lake Pillsbury later in the year. Water availability moving forward is expected to be similar to dry year conditions experienced in 2020 and 2021.
"The safety of our hometowns is PG&E’s most important responsibility, and this includes the company’s dedicated team of geoscience and engineering experts regularly performing updated seismic analyses and modeling of its dams based on regional and site-specific data. While Scott Dam is not at risk of imminent failure, models with updated parameters show an increased risk around seismic performance. As a result, PG&E is taking steps to reduce the risk.
"We recognize the impacts that reduced water storage in Lake Pillsbury will have. We’re committed to public and environmental safety and are committed to working closely with resource agencies and water districts to address any impacts associated with this safety measure.
"Again, the seismic risks for the Scott Dam remain low and the decision to not close the spillway gates helps reduce risk."
PG&E usually closed the Scott Dam gates in April of each year, allowing spring runoff and snowmelt to raise water levels in Lake Pillsbury to be released throughout the summer and early autumn for Eel River flows. A small portion of the flows were historically diverted through the Potter Valley Project to generate power, with the water being released in the East Fork Russian River in Potter Valley. This water made its way downstream, into and through Lake Mendocino and into the mainstem Russian River. Over the years, the State Water Resources Control Board issue water rights for this diverted water to water users in Mendocino and Sonoma Counties.
On April 27, 2023, PG&E held a Town Hall Meeting on zoom, providing more information on the announcement and of the plan to decommission the Potter Valley Project. It was noted the Division of Safety of Dams (DSOS) under the California Natural Resources Agency Department of Water Resources had concurred with the PG&E's plan for reducing water storage levels in Lake Pillsbury (behind Scott Dam.) PG&E stated it planned to proceed with DSOS processes according to seismic studies and risk analysis.
PG&E's announcement based on updated seismic analysis of Scott Dam suggested a higher level of risk than previous evaluations, prompting a change in operations. PG&E would now release more water from Lake Pillsbury throughout the rainy season, allowing it to flow into the Eel River this spring instead of keeping it behind Scott Dam. This resulted in less water being available for summer and autumn releases, including diversions to the Russian River watershed.
PG&E issued this press release on 3/16/23: Water Levels at Lake Pillsbury to be Lower this Year.
The following provide further background and information:
2023, 3-21 Thompson let to FERC re Seismic Scott Dam impacts.pdf2023, 3-28 FERC response to PGE Seismic Scott Dam actions.pdf2023, 4-3 Lake County letter to FERC re Seismic issue.pdf2023, 4-4 Lake County letter to FERC re Seismic issue.pdf
2023, 4-12 DSOD to PGE, Scott Dam seismic.pdf2023, 4-28 FERC to PGE, Seismic Stability and IRRM Letter.pdf2023, 6-12 FERC reminder of report due.pdf2023, 6-13 PGE Seismic report comment response letter.pdf2023, 6-13 PGE Seismic report comment response letter attachment.pdf2023, 6-13 PGE Seismic report comment response letter attachment.pdf2023, 6-30 FOER Response to 4-3-23 Lake County Comments on Scott Dam ops.pdf2023, 10-18 PG&E Scott Dam DSOD inspection report.pdf2023, 10-18 PG&E Van Arsdale Dam DSOD inspection report.pdf2024, 4-23 Request for Review of CEII Filings regarding PVP.pdf2024, 7-1 PGE response to FERC RE-Scott Dam safety.pdf
Related Articles:
2023, 3-17 Press Dem - Scott Dam gates to stay open.pdf- Press Democrat article - Scott Dam gates to stay open, meaning Lake Pillsbury diversions to remain at drought levels, 3/16/23.
- KZYX - Spillway gates on Scott Dam to remain open, curtailing flow into East Branch, 3/18/23